Ngaio Gardens – November Build Update

We’re pleased to share the latest construction progress at Ngaio Gardens.

Block A (Houses 1, 2 & 3):

  • Gib fixing and plastering have been completed.

Block B (Houses 2, 4 & 5):

  • Roof trusses are now in place, and the pre-roof inspection has been completed.

Block C (Houses 6 & 7):

  • Exterior cladding has been completed.

Block D (Houses 8 & 9):

  • Exterior cladding is nearing completion.

Block E (Houses 10 & 11):

  • Waterproofing has been completed.

Block F (Houses 12 & 13):

  • Electrical pre-wiring has been completed.