Marriner Street October 2026
October 20, 2026
21 & 23 Marriner Street is looking great from the street!
Since our last update:
Block 1:
- Waterproofing completed
- Underfloor heating installed
- Landscaping has commenced.
Block 2:
- Kitchen installation underway.
- Landscaping has commenced.
Block 3:
- Exterior painting completed
- Balcony works now underway.
- Internal painting completed
Driveway: Works have commenced.